Project Performance Analysis of Housing Development Using the Earned Value Method (Case Study: Safira Gold Mansion Housing Project, Appenzell Two-Storey Type)
Keywords:
Earned Value Method, Housing Project, Project Delay, Schedule Performance Index, Time PerformanceAbstract
The Safira Gold Mansion Appenzell two-storey housing project in Sukodono, Sidoarjo Regency experienced delays in project implementation compared to the planned schedule. The project applies an indent housing development system, where construction activities are carried out gradually based on unit sales, causing uneven work progress between housing units. At week 43, the planned cumulative progress was targeted at 57.10%, while the actual progress only reached 33.72%, resulting in a project delay deviation of 23.38%. This study aims to analyze the estimated project completion time based on actual project performance using the Earned Value Method. The research used secondary project data consisting of the S-curve, time schedule, weekly progress reports, and project cost realization data. Project performance analysis was conducted using Planned Value , Earned Value, Actual Cost, and Schedule Performance Index (SPI) indicators. The analysis results indicate that the project experienced schedule delays with an SPI value below 1, which reflects that the actual project progress was slower than planned. The delay condition was influenced by operational constraints, including finishing work delays, limited effective working days, and non-uniform construction progress between housing units. Based on the EVM analysis, the estimated project completion duration exceeded the planned schedule, indicating that project time performance had not been achieved optimally. The application of the Earned Value Method was able to provide a quantitative evaluation of project schedule performance and identify deviations between planned and actual project implementation.