https://conference.untag-sby.ac.id/index.php/icef-tags/issue/feedProceeding International Civil Engineering Forum Untag Surabaya2026-09-23T04:16:46+00:00Open Journal Systems<p>PROCEEDING</p>https://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7064Identification of Dominant Architectural Cost Components through Value Engineering: A Case Study of the Mie Gacoan Sorong–Nangka Restaurant Project2026-09-04T07:06:18+00:00Putri Dwi Rahayu[email protected]Budi Witjaksana[email protected]Dika Ayu Safitri[email protected]<p><em>Construction projects in Eastern Indonesia, particularly in Sorong Regency, face several major challenges, including high logistics costs, limited material supply chains, and the highest Construction Cost Index (CCI) in Indonesia. The construction project of the Mie Gacoan Sorong–Nangka outlet, a large-scale commercial restaurant building with a total building area of 509.4 m² on a 2,000 m² site, provides a relevant case for cost optimization through a Value Engineering (VE) approach. This study focuses on identifying the architectural work components that contribute most significantly to project costs as the basis for implementing VE. A quantitative descriptive approach was applied using Pareto analysis on the project’s Budget Plan (RAB) and Bill of Quantity (BOQ) documents to determine the dominant architectural work items. The analysis results show that the total architectural work cost reached IDR 849,736,345.71. Floor, wall, and ceiling finishing works accounted for 74.50% (IDR 633,014,041.21) of the total architectural cost, followed by railing, door, and window frame works at 17.62% (IDR 149,760,279.93), while painting works contributed 7.88% (IDR 66,962,024.57). Based on the Pareto 80–20 Principle, floor, wall, and ceiling finishing works were identified as the primary high-cost item and became the main priority for further Value Engineering analysis. These findings confirm that the concentration of costs within a single architectural work group provides a strong and focused foundation for the next phases of the VE process.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7065Service Quality Analysis of Damri Transportation on the Purabaya Terminal – Juanda Airport Route Using Fuzzy Servqual and Importance Performance Analysis (IPA) Methods2026-09-04T07:21:33+00:00Luh Putu Rewinda Wiriandeni[email protected]Hanie Teki Tjendani[email protected]Budi Witjaksana[email protected]<p><em>The Damri transportation service operating on the Purabaya Terminal – Juanda Airport route is currently experiencing a low level of fleet capacity utilization. This condition is indicated by the load factor value, which remains below the ideal public transportation standard of 70% based on the Decree of the Director General of Land Transportation Number 687 of 2002. This condition indicates that the quality of service and supporting facilities still need to be improved in order to increase public interest in using the Damri airport shuttle bus service. Therefore, this study aims to identify service gaps and determine service improvement priorities based on the importance and performance levels of service attributes. The research method used in this study is descriptive quantitative. Service gap analysis was conducted using the fuzzy servqual method to identify the differences between passenger perceptions and expectations regarding service quality. Furthermore, service improvement priorities were determined using the Importance Performance Analysis (IPA) method based on the importance and performance levels of service attributes. Data collection in this study was carried out through questionnaires distributed to 95 respondents. The results showed that the highest gap value was found in the disabled passenger facilities variable with a value of (-1,74), while the lowest gap value was found in the vehicle condition/feasibility variable with a value of (-0,17). Based on the Importance Performance Analysis (IPA), four indicators were categorized as the main priorities for improvement: B1 security disturbance information (Security), C5 service information (Reliability/Regularity), D1 waiting facilities (Comfort), and F1 facilities for disabled passengers (Equality).</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7066Cost and Schedule Performance Analysis Using Earned Value Method in the Warehouse MCC Room Construction Project at PT. Omya Plant Paciran Lamongan2026-09-07T04:12:40+00:00Aris Lukmanul Khakim[email protected]Budi Witjaksana[email protected]Jaka Purnama[email protected]<p><em>Construction projects require integrated cost and schedule control because deviations between planned and actual performance may affect project success. The Warehouse MCC (Motor Control Center) Room construction project at PT. Omya Plant Paciran Lamongan is an industrial facility project that requires careful monitoring of cost and time performance. This paper focuses on one research objective: to obtain project cost and schedule performance using the Earned Value Method through the indicators of Cost Variance (CV), Schedule Variance (SV), Schedule Performance Index (SPI), Cost Performance Index (CPI), Estimate at Completion (EAC), and Estimate Completion Date (ECD). The study was designed as a descriptive quantitative case study using secondary project data, including the time schedule, budget plan, weekly progress reports, and actual cost records. The analysis integrates Planned Value (PV), Earned Value (EV), and Actual Cost (AC) to calculate variance and performance index indicators. Since the submitted thesis document has not yet included a completed Chapter 4 with actual project calculation results, the results section presents a full-paper analytical framework, calculation matrix, and interpretation model that can be directly completed once weekly project data are available. The paper concludes that the Earned Value Method provides a systematic basis for evaluating project cost and schedule performance in the Warehouse MCC Room construction project.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7067The Hidden Cost of Quality Failure in Road Construction: Evidence from a Strategic Infrastructure Project in Batam, Indonesia2026-09-07T04:24:35+00:00Martina Magdalena Tuulima[email protected]Hanie Teki Tjendani[email protected]Bambang Trigunarsyah[email protected]<p>Quality control in Indonesian road construction remains structurally reactive: risk management and quality assurance operate as independent functions without a shared analytical framework, leaving oversight resources uniformly distributed regardless of actual risk exposure. This study examines how Risk-Based Quality Management (RBQM) was applied throughout the Hang Tuah Road Widening Project in Batam City, Indonesia (a high-complexity arterial intervention with a final contract value of IDR 68.28 billion under continuous traffic conditions), and identifies the structural factors constraining or supporting its effectiveness. A retrospective single-case study design is employed, drawing on 34 primary project documents and semi-structured interviews with nine key informants, supplemented by Failure Mode and Effects Analysis (FMEA) incorporating a Quality-Severity modification that isolates specification non-conformance magnitude as the primary risk scoring dimension. Findings establish that none of the five core RBQM elements was formally operationalized at any project stage, despite concurrent availability of four structural enabling conditions that remained collectively underutilized. Three dominant quality risk events were identified, all classified as High priority with RPN-Quality values ranging from 336 to 432; Detection scores of 8 on two events confirm the monitoring architecture was structurally incapable of intercepting deviations before they became irremediable. Two governance deficiencies emerged as primary determinants: the absence of a formal risk register as the calibrating instrument for proportionate oversight allocation, and exclusive reliance on binary pass/fail evaluation incapable of detecting adverse parameter trends prior to specification breach. These findings yield two practitioner-oriented outputs: a Contextual RBQM Model structuring five sequentially interdependent governance elements, and an RBQM Implementation Guideline translating the model into operational steps for comparable road infrastructure projects.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7068Assessment of Precast Structural Design for Economy and Time Savings in the Borong Hospital Design and Build Initiative2026-09-07T04:47:52+00:00Aldo Salam Lubis[email protected]Ony Frengky Rumihin[email protected]Buntara Sthenly Gan[email protected]<p>The erection of hospital edifices necessitatesbuilding techniques that fulfill the criteria forexcellence, economical expenditure, and swift projectfinalization. One strategy that is commonly utilized isthe adoption of precast concrete frameworks, whichare seen as effective in enhancing productivity andshortening the period of on-site construction. This research intends to assess how theintegration of a precast structural frameworkinfluences cost and time efficiency within the BorongHospital Design and Build Initiative. The studyutilized a quantitative descriptive approach byperforming a comparative investigation betweenprecast structural design and traditional structuraldesign, focusing on working blueprints, costprojections (RAB), and project timelines. The evaluation centered on primary structural elements, such as columns, beams, and floor slabs, to ascertainthe degree of cost savings and time efficiencyachieved. The findings demonstrate that the use ofprecast structures can lead to a decrease in the timelinefor structural tasks, as the manufacturing processoccurs concurrently with on-site constructionactivities, enhancing project time efficiency by a totalof 46 days, which is equivalent to 20.91%. Moreover, the incorporation of precast structures offers costadvantages due to diminished needs for formwork,labor, and wastage of construction materials, leadingto savings of IDR 1,150,515,798.29, representing 5.18%of the overall structural expenditure. Hence, precaststructural design can be regarded as a viable option forenhancing the performance of construction endeavors,especially in hospital projects that demand highquality standards and strict deadlines.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7069Comparative Analysis of Occupational Safety and Health (OSH) Costs: The Project Method vs. Circular Letter No. 11/SE/M/2019 In Building Projects2026-09-07T06:17:12+00:00Nursaid Nursaid[email protected]Budi Witjaksana[email protected]Hanie Teki Tjendani[email protected]<p>Occupational Safety and Health (OSH) is a critical aspect of construction project implementation, aimed at reducing the risk of workplace accidents and creating a safe, comfortable, and productive work environment. The implementation of OSH in construction projects requires appropriate budget allocation to ensure that all occupational safety programs can be carried out optimally. This study aims to compare project-based OSH costs with OSH costs based on the Minister of Public Works and Public Housing Circular Letter No. 11/SE/M/2019 in building construction projects. The research method used is quantitative descriptive with a case study approach. Data were obtained through field observations, interviews, and project documents in the form of Cost Estimates (RAB) and project OSH documents. Analysis was conducted by calculating OSH costs using the project method and then comparing them with calculations based on Circular Letter No. 11/SE/M/2019. The results of the study indicate that OSH costs using the project method amount to Rp15,500,000, whereas those based on Circular Letter No. 11/SE/M/2019 amount to Rp27,500,000. This difference arises because the cost components based on SE No. 11/SE/M/2019 are calculated in greater detail and are more comprehensive. Consequently, the application of OSH costs in accordance with government regulations is considered more optimal in supporting the implementation of workplace safety and enhancing the effectiveness of risk control in construction projects.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7070Traffic Load Influence on Pavement Condition Deterioration Using the Pavement Condition Index Method2026-09-07T06:22:25+00:00Yeyen Dwi Affri Rahmandhani[email protected]Risma Marleno[email protected]Laksono Djoko Nugroho[email protected]<p>Road pavement deterioration remains a major challenge for urban transportation infrastructure in rapidly growing metropolitan areas. Surabaya, as one of Indonesia’s largest metropolitan cities, experiences substantial traffic growth dominated by heavy vehicles and freight transportation. This study investigates the influence of traffic loading on pavement condition deterioration along Gunungsari Road, Surabaya, East Java, using the Pavement Condition Index (PCI) method and AASHTO 1993 traffic load analysis. The study integrates Average Daily Traffic (ADT), vehicle composition, Equivalent Single Axle Load (ESAL), and Cumulative Equivalent Standard Axle (CESA5) calculations with field-based pavement condition assessment. The research corridor was divided into ten observation segments, each evaluated visually according to ASTM D6433-18 standards. Traffic surveys were conducted for seven consecutive days to determine traffic characteristics and cumulative traffic loading. Statistical analysis was performed using correlation and linear regression to determine the relationship between traffic loading and PCI values. The results indicate that heavy vehicles contributed disproportionately to cumulative pavement damage despite representing a smaller portion of total traffic volume. PCI values ranged from 36 to 78, indicating varying pavement conditions from very poor to good categories. The regression analysis revealed a strong negative correlation between cumulative ESAL and PCI values, demonstrating that increased traffic loading significantly accelerates pavement deterioration. Several segments exceeded the design traffic loading threshold, resulting in accelerated distress such as alligator cracking, rutting, potholes, and surface deformation. The findings confirm that traffic loading is a dominant factor influencing pavement performance degradation on urban arterial roads. This study provides practical insights for pavement maintenance prioritization, traffic management strategies, and infrastructure planning in high-traffic metropolitan corridors.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7072Evaluation of Flexible Pavement Surface Roughness Values Using a Smartphone Accelerometer Sensor-Based Application on the Deandels Road Section, Probolinggo Regency2026-09-07T06:48:50+00:00Rizky Yudha Hardiansyah[email protected]Hanie Teki Tjendani[email protected]Sajiyo Sajiyo[email protected]<p>Road surface conditions that experience quality degradation can affect the level of comfort, safety, and operational efficiency of transportation. One parameter used to evaluate the functional condition of roads is the International Roughness Index (IRI), which is capable of describing the level of road surface roughness objectively. This study aims to analyze the level of road damage using the International Roughness Index (IRI) method based on the Roadroid application as a basis for determining road repair treatment on the Deandels Road Section of Probolinggo Regency. The research method was carried out through field surveys using a smartphone-based Roadroid application by utilizing the accelerometer sensor of a four-wheeled vehicle at a speed of 20-40 km/h. Data collection was carried out twice in each road direction and analyzed per segment along 100 meters. The results showed that the average IRI value on the Deandels Road Section was 5.26 m/km, which falls into the moderate category based on Bina Marga standards. The distribution of road conditions shows 46.66% of segments are in good condition, 37.77% in moderate condition, 13.33% in minor damage condition, and 2.22% in severe damage condition. Based on the evaluation results, the types of treatment recommended include routine maintenance, periodic maintenance, rehabilitation, and reconstruction according to the level of damage in each segment. This study shows that the Roadroid application can be used as an effective and efficient method in evaluating road conditions and supporting appropriate road treatment decision-making.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7073Road Pavement Condition Assessment Using the Bina Marga Method: A Case Study of the Babat–Lamongan Highway (Plaosan Segment, Km 24.5)2026-09-07T06:54:20+00:00M. Hidayat[email protected]Intan Mayasari[email protected]Annisa' Carina[email protected]<p>Road infrastructure plays a vital role in supporting community mobility, goods distribution, and regional economic development. Increasing traffic volume, particularly heavy vehicle traffic, contributes to pavement deterioration manifested through various forms of road distress. This study aims to evaluate pavement conditions and determine maintenance priorities using the Bina Marga Method on the Babat–Lamongan Highway, specifically at STA 24+500–25+500, covering an approximately 1 km road segment. The research employed a quantitative approach through field surveys to identify the type, severity, and extent of pavement damage. The collected data were analyzed based on the pavement condition assessment parameters and Priority Ranking (Urutan Prioritas/UP) specified in the Bina Marga guidelines. The results revealed several types of pavement distress, including alligator cracking, ravelling, deteriorated patches, rutting, depressions, and potholes. The pavement condition assessment produced an average condition value of 3.5, while the Priority Ranking value was calculated at 7.5 and rounded to 7. According to the Bina Marga classification system, the studied road section remains serviceable and is categorized as requiring routine maintenance. Recommended maintenance measures include crack sealing, pothole patching, rehabilitation of damaged patches, shoulder repairs in depressed areas, surface treatment for ravelling, and periodic drainage maintenance. The findings provide valuable information for developing effective road maintenance strategies to preserve pavement performance, maintain serviceability, and prevent further deterioration.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7074Determination of Criteria Weights for Provincial Road Handling Priority in Gresik Regency Using the Analytical Hierarchy Process2026-09-07T07:04:48+00:00Fajar Ilman Tama[email protected]Ony Frengky Rumihin[email protected]Iswandaru Widyatmoko[email protected]<p>Provincial road handling requires a transparent basis for determining which criteria should receive the strongest consideration in maintenance planning, especially when road condition, traffic volume, connectivity, and regional development functions interact in one decision problem. This article focuses only on the first research question of the study, namely how to determine the weights of influential criteria for provincial road handling priority in Gresik Regency using the Analytical Hierarchy Process (AHP). The study used a quantitative decision-making approach based on pairwise comparison questionnaires and geometric mean aggregation. The criteria assessed were road condition and traffic volume, road connectivity, industrial development areas, goods and services logistics areas, and economic areas with settlement development. The results show that road condition and traffic volume are the most influential criteria, with a weight of 0.293 or 29.30%. Road connectivity ranks second with 0.232 or 23.20%, followed by industrial development areas with 0.189 or 18.90%, logistics areas with 0.182 or 18.20%, and economic and settlement development areas with 0.104 or 10.40%. The consistency test produced a consistency ratio of approximately 0.0203, which is below the acceptable threshold of 0.10. Therefore, the pairwise comparison matrix is consistent, and the resulting weights can be used as a methodological basis for subsequent priority analysis of provincial road handling in Gresik Regency.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7075Analysis of Delays and Queue Lengths Caused by the Closure of Railway Crossings: Study Case of Jaksa Agung Suprapto Road, Lamongan Regency2026-09-08T06:22:24+00:00Bajuri Afandi[email protected]Agus Setiawan[email protected]Intan Mayasari[email protected]<p>At-grade railroad crossings can cause traffic disruptions in the form of delays and long vehicle queues. This study aims to analyze the impact of railroad crossing closures on traffic performance on Jaksa Agung Suprapto Road, Lamongan Regency. The research method employed field surveys and analysis based on the 2023 Indonesian Road Capacity Guidelines (PKJI). The results show that the highest traffic volume reached 1,660 vehicles per hour in the Babat–Surabaya direction and 1,743 vehicles per hour in the Surabaya–Babat direction. Road capacity is 1,878 vehicles per hour with saturation levels of 0.88 and 0.92, respectively. The longest duration of a level crossing closure was 531 seconds. The maximum delay reached 578 seconds in the direction of Surabaya and 248 seconds in the direction of Babat, with average queue lengths of 130.41 meters and 104.53 meters, respectively. The results of the study indicate that the longer the duration of the level crossing closure and the higher the vehicle volume, the greater the delay and queue length. These conditions indicate that level crossings remain a factor affecting traffic performance on the Jaksa Agung Suprapto Road section in Lamongan Regency.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7076Structural Quality Comparison of Bungur Bridge T-Girder Using Conventional BJTS 420B and Ultra High Strength Steel (UHSS) Reinforcement2026-09-08T06:34:02+00:00Kholilurrohman Kholilurrohman[email protected]Budi Witjaksana[email protected]Hanie Teki Tjendani[email protected]<p>Bungur Bridge in Pamekasan is a 15.00 m short-span bridge on the provincial road network that requires reliable structural quality and controlled constructability. This paper is derived from the first research objective of the thesis and focuses only on analyzing the structural quality comparison of the T-girder between conventional BJTS 420B reinforcement and Ultra High Strength Steel (UHSS) reinforcement. A descriptive quantitative case-study method was used based on bridge geometry, material parameters, load analysis, and reinforced concrete section checks. The analysis applied concrete K-500 or f'c = 41.50 MPa, conventional reinforcement with fy = 420 MPa, UHSS reinforcement with fy = 700 MPa, and the critical ultimate moment of 3,702.46 kNm. The results show that the conventional alternative requires 29-D25 tension bars and produces a flexural capacity of 3,898.00 kNm, while the UHSS alternative requires 17-D25 tension bars and produces 3,810.93 kNm. Both alternatives satisfy flexural, shear, and deflection controls, with maximum calculated deflections of 0.0340 m for conventional reinforcement and 0.0380 m for UHSS, below the allowable limit of 0.0625 m. The UHSS alternative reduces reinforcement congestion and decreases the total reinforcement weight for six girders from 17,473.61 kg to 9,933.21 kg. Therefore, UHSS can be considered structurally feasible for improving the quality and constructability of the Bungur Bridge T-girder, provided that detailing, anchorage, cracking, and field quality control are carefully verified.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7077Analysis and Modelling of the Sroyo Village Composite Bridge Superstructure Based on SNI 1725:20162026-09-08T06:44:00+00:00Bryan Septian Ari Pratama[email protected]Donny July Prasetyo[email protected]Annisa' Carina[email protected]<p>Structural design calculations for composite bridges in rural areas are still rarely implemented, resulting in unverified structural safety. This condition applies to the composite bridge in Sroyo Village, which serves as a critical link between Sroyo Village and Banjaranyar Village. Furthermore, the physical condition of the existing bridge is deteriorating, potentially endangering its users. This study aims to conduct a comprehensive structural analysis and modelling of the composite bridge superstructure to meet established safety and structural feasibility standards. This research was carried out using two methods: analytical manual calculations and computer-based structural modelling utilizing SAP2000. The loading and design parameters conform to SNI 1725:2016, supported by RSNI T-03-2005 and SNI 2847:2019. The structural internal forces were calculated manually and then integrated into the SAP2000 software to validate the analytical results and simulate the bridge behavior. Based on the structural analysis and modelling of the superstructure, the ultimate internal forces obtained are lower than the nominal capacity of the bridge, with a Demand Capacity Ratio (DCR) < 1.0. Consequently, it can be concluded that the structural design of the Sroyo Village composite bridge satisfies the safety and structural feasibility criteria in accordance with national regulations.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7078Comparative Efficiency Assessment of Hot-Rolled and Welded Built-Up H-Beam Columns Based on Compressive Capacity and Cost-to-Capacity Ratio2026-09-08T06:50:46+00:00Febri Novianto[email protected]Ony Frengky Rumihin[email protected]Buntara Sthenly Gan[email protected]<p>The selection of steel column sections during the design stage should consider not only structural capacity but also the economic efficiency achieved. This study aims to evaluate the efficiency of hot-rolled and welded built-up H-beam profiles based on their compressive capacity and cost per capacity. The study was conducted on the main steel columns of the Warehouse Gateway J&T Solo structure with an effective column length of 12 m. The evaluation consisted of nominal compressive capacity calculations in accordance with SNI 1729:2020, numerical analysis using SAP2000 to determine ultimate compressive capacity, and fabrication cost analysis based on the Unit Price Analysis (AHSP) method. The efficiency of each profile was assessed using the ratio of fabrication cost to ultimate compressive capacity. The results indicate that the hot-rolled profile achieved a nominal compressive capacity of 162,743 kgf and an ultimate compressive capacity of 193,015 kgf, whereas the welded built-up profile achieved a nominal compressive capacity of 158,710 kgf and an ultimate compressive capacity of 189,465 kgf. In terms of fabrication cost, the hot-rolled profile exhibited a lower unit fabrication cost of IDR 23,324/kg compared with IDR 23,885/kg for the welded built-up profile. The cost-per-capacity evaluation yielded values of 13,746 IDR/kN and 13,784 IDR/kN for the hot-rolled and welded built-up profiles, respectively. Based on these findings, the hot-rolled profile demonstrates slightly better efficiency than the welded built-up profile under the conditions considered in this study.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7079Project Performance Analysis of Housing Development Using the Earned Value Method (Case Study: Safira Gold Mansion Housing Project, Appenzell Two-Storey Type)2026-09-08T06:59:08+00:00Axel Prasetya Adoe[email protected]Budi Witjaksana[email protected]Dika Ayu Safitri[email protected]<p>The Safira Gold Mansion Appenzell two-storey housing project in Sukodono, Sidoarjo Regency experienced delays in project implementation compared to the planned schedule. The project applies an indent housing development system, where construction activities are carried out gradually based on unit sales, causing uneven work progress between housing units. At week 43, the planned cumulative progress was targeted at 57.10%, while the actual progress only reached 33.72%, resulting in a project delay deviation of 23.38%. This study aims to analyze the estimated project completion time based on actual project performance using the Earned Value Method. The research used secondary project data consisting of the S-curve, time schedule, weekly progress reports, and project cost realization data. Project performance analysis was conducted using Planned Value , Earned Value, Actual Cost, and Schedule Performance Index (SPI) indicators. The analysis results indicate that the project experienced schedule delays with an SPI value below 1, which reflects that the actual project progress was slower than planned. The delay condition was influenced by operational constraints, including finishing work delays, limited effective working days, and non-uniform construction progress between housing units. Based on the EVM analysis, the estimated project completion duration exceeded the planned schedule, indicating that project time performance had not been achieved optimally. The application of the Earned Value Method was able to provide a quantitative evaluation of project schedule performance and identify deviations between planned and actual project implementation.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7080Soil and Water Conservation Strategy for Mitigating Erosion and Flood Potential in the Tukad Kaliakah Sub-Watershed Using a GIS-Based USLE Approach2026-09-08T07:04:32+00:00I Made Wiwin Juni Aryantha[email protected]Esti Wulandari[email protected]Andi Patriadi[email protected]<p>Land use change within a watershed can reduce infiltration capacity and simultaneously elevate erosion and flood potential. This study aims to formulate soil and water conservation strategies for the Tukad Kaliakah Sub-watershed, Jembrana Regency, Bali Province, based on an integrated assessment of erosion, sedimentation, and flood potential. A quantitative approach combining GIS-based spatial analysis in QGIS with hydrological analysis was applied over an area of 11.88 km2. Erosion was estimated using the GIS-based Universal Soil Loss Equation (USLE), sedimentation through the Sediment Delivery Ratio, and flood potential through design flood discharge using the Nakayasu Synthetic Unit Hydrograph. Between 2012 and 2023, mixed gardens declined from 55.69% to 46.91% and paddy fields from 41.45% to 16.80%, while settlements expanded from 2.87% to 36.29%. These changes raised the mean erosion rate from 24.19 to 26.68 tonnes/ha/year and sediment yield from 5,604 to 6,181 tonnes/year, while the design flood peak discharge reached 69.91 m3/s for the 100-year return period. Accordingly, vegetative conservation through agroforestry on the 169.59 ha priority area, complemented by sediment control structures, is recommended to reduce erosion, sedimentation, and flood potential in a sustainable manner.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7081Occupational Safety and Health Risk Level and Priority Analysis Using Risk Breakdown Structure in the Construction of the RKB Building at MIN 5 Tulungagung2026-09-08T07:10:17+00:00Eko Budi Utomo[email protected]Budi Witjaksana[email protected]Jaka Purnama[email protected]<p>Educational building construction has considerable Occupational Safety and Health (OSH) risk potential because it involves workers, equipment, materials, work methods, and dynamic project environmental conditions. This study aims to identify the risk level and determine the priority ranking of risk factors causing work accidents in the physical construction work of the RKB Building at MIN 5 Tulungagung using the Risk Breakdown Structure (RBS) method. Data were collected through field observation, project document review, and questionnaires distributed to 15 respondents directly involved in the project. The questionnaire instrument was tested using validity analysis and Cronbach's Alpha reliability testing before risk calculation. Risk factors were classified into five main categories: environmental, human, equipment, work method, and management/organizational factors. The results identified 20 OSH risk factors. Four risks were classified as high, while sixteen risks were classified as medium. The highest risk factor was the lack of internal communication and coordination among project parties, with a risk value of 12.240, followed by extreme weather at 11.778, dust exposure due to construction activities at 10.444, lack of worker skills at 10.427, and not using personal protective equipment at 9.747. The findings indicate that RBS can systematically map OSH risk sources and support risk priority determination in educational building construction projects.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7082An Operational Analysis of Pre-loading Capacity Constraints at the Ketapang-Gilimanuk Crossing2026-09-08T07:16:11+00:00Abdurrahman Mahdy Al Faishal[email protected]Hanie Teki Tjendani[email protected]Budi Witjaksana[email protected]<p>Ketapang Ferry Port is a primary-class port serving as a vital link for land connectivity between the islands of Java and Bali. The integration of the Trans-Java Toll Road has triggered induced demand, resulting in a significant surge in vehicle volume. This study aims to determine the ideal capacity for the "ready-to-load" parking area based on operational performance, specifically by evaluating the Berth Occupancy Ratio (BOR) for Landing Craft Machine (LCM) docks. Furthermore, this study analyzes the economic feasibility of expanding the LCM parking facilities. The research methodology employs the Berth Occupancy Ratio (BOR) analysis—in accordance with the Decree of the Director General of Land Transportation (KP-DRJD 539/2022) and UNCTAD standards—alongside calculations for ready-to-load parking capacity. Economic feasibility is assessed using Net Present Value (NPV), Internal Rate of Return (IRR), and Benefit-Cost Ratio (BCR) parameters. The results indicate that the required "ready-to-load" parking area for the LCM dock at Ketapang Ferry Port is 3,825 $m^2$ for Class VII vehicles and 5,346 $m^2$ for Class VIII vehicles. The operational performance of the LCM dock, based on the BOR, is 46% during normal conditions and 53% during peak seasons. Economic feasibility analysis for the parking area expansion yielded positive results across all tested interest rates. With a Benefit-Cost Ratio (BCR) greater than 1.00 and an Internal Rate of Return (IRR) reaching 46%, the project is deemed highly feasible for implementation.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7084Analysis the Level of AKDP Bus Service Quality (Madiun-Ponorogo Route) Based on User Satisfaction Level Using the Importance Performance Analysis (IPA) Method2026-09-08T07:28:41+00:00Irma Kamaliah[email protected]Budi Witjaksana[email protected]Hanie Teki Tjendani[email protected]<p>The weakening competitiveness of intercity public transportation compared to private vehicles and digital-based mobility platforms demands a systematic and measurable evaluation of service quality. This study aims to analyze the gap between the expectations and satisfaction of users of intercity bus services within the province (AKDP) on the Madiun-Ponorogo route through the Importance Performance Analysis (IPA) method. A quantitative descriptive approach was applied to 90 respondents selected through simple random sampling, with data collection using structured interviews and a 27-attribute Likert scale questionnaire referring to the Minimum Service Standards (SPM) regulations. The Cartesian diagram mapping of IPA identifies 8 attributes in Quadrant I that require urgent improvement, with the lowest level of suitability in the waiting time attribute at 68% and service information at 74%. The average overall suitability level was recorded at 90%, with a performance value (X̄) of 2.87 and an importance value (Ȳ) of 3.22. These findings indicate a significant gap between user expectations and the actual performance of the service, particularly in the dimensions of timeliness and information transparency, so that priority-based improvement interventions by operators and policymakers become a necessity.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7085Time Efficiency Analysis OF Riverbank Protection Project Acceleration Using THE Critical Path Method (CPM) in the Masangan River, Pasuruan Regency2026-09-09T02:56:07+00:00Ahzam Zarkasy Septian Danu[email protected]an Patriadi[email protected]Esti Wulandari[email protected]<p>Time delay is one of the most common issues encountered in construction projects and can significantly affect project performance and efficiency. In the riverbank protection project of the Masangan River, Pasuruan Regency, construction activities experienced delays due to unfavorable weather conditions, fluctuating river discharge, and limited effective working hours caused by tidal influences. These constraints hindered project progress and prevented several activities from being completed according to the planned schedule. Therefore, an effective scheduling and acceleration strategy is required to optimize project completion time. This study aims to analyze the time efficiency achieved through project acceleration using the Critical Path Method (CPM). The CPM approach was employed to identify critical activities that directly influence the overall project duration through network scheduling analysis, including the determination of Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) times, as well as the identification of the critical path. Activities located on the critical path were prioritized in the acceleration strategy to reduce the overall project duration while maintaining logical relationships among project activities. The analysis was supported by Microsoft Project software to facilitate accurate scheduling and project control. The results of this study are expected to demonstrate the extent of time efficiency that can be achieved through the application of CPM-based acceleration strategies. Furthermore, the findings are intended to provide practical guidance for project managers in controlling construction schedules and serve as a reference for similar riverbank protection projects facing time-performance challenges.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7086Analysis of Potential Demand for Tourist Transportation as A Support for Tourist Mobility at Lut Tawar Lake, Central Aceh Regency2026-09-09T03:04:39+00:00Mareza Bagus Candra Pradana[email protected]Hanie Teki Tjendani[email protected]Bambang Trigunarsyah[email protected]<p>A potential demand analysis was conducted to determine the number of tourist transportation vehicles required for operational purposes, ensuring optimal service delivery. This ensures that the fleet is neither too small, which could lead to underserved tourists, nor too large, which could potentially lead to operational losses. The demand analysis was conducted through an interview survey of tourists in the Pante Menye Danau Lut Tawar tourist area, Central Aceh Regency. The survey results revealed that the majority of tourists expressed a willingness to switch modes of transportation to tourist transportation. The analysis of the willingness to switch modes showed that 136 tourists, or 64%, expressed a willingness to use tourist transportation to reach tourist locations, while 77 tourists, or 36%, expressed a reluctance to switch modes. This finding indicates that the majority of tourists have a positive attitude toward using tourist transportation services as an alternative means of transportation to tourist areas. The calculation of potential population demand was obtained by multiplying the total number of tourists who expressed a willingness to switch to tourist transportation by the expansion factor. The analysis yielded a potential population demand of 664 tourists. The largest number of requests to the Pante Menye Lake Lut Tawar tourist area came from external zone 16, with 609 tourists, while in the internal zone, the largest number of requests came from zone 2, with 16 tourists. These results indicate a significant potential need for tourist transportation services, necessitating fleet planning tailored to the characteristics of tourist demand</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7088Beyond Time and Cost: Integrating Quality into Construction Schedule Optimization Using a Time-Cost-Quality Trade-Off Approach2026-09-09T06:14:45+00:00Lila Ayu Ratna Winanda[email protected]Tio Boanmora Nabasa Rajagukguk[email protected]<p>Construction project acceleration is commonly adopted to meet project deadlines; however, reducing project duration often leads to increased costs and potential declines in quality. Existing optimization approaches primarily focus on the relationship between time and cost, with limited attention given to quality considerations. Therefore, this study aims to integrate quality into construction schedule optimization to identify a more balanced acceleration strategy. A quantitative case study approach was employed using project scheduling, cost, and quality data obtained from a building construction project in Indonesia. Critical activities were identified using project scheduling software, while acceleration scenarios were developed through overtime-based crashing analysis. Quality performance was assessed through expert judgement and incorporated into the optimization process using a spreadsheet-based optimization tool. The result showed that the normal project condition required 236 days with a total cost of IDR 7,087,959.56 and a quality level of 100%. The Time-Cost Trade-Off approach reduced to IDR 7,478,116,793.64 and lowered quality performance to 87%. Meanwhile, the Time-Cost-Quality Trade-Off approach identified 230 days as the optimal duration, with a total cost of IDR 7,152,985,765.24 and a quality level of 98%. The findings indicate that the shortest project duration does not necessarily provide the most effective solution. Incorporating quality into schedule optimization offers a more comprehensive framework for selecting construction acceleration strategies.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7089Integrated Flood Risk Management in Bridge Construction: A CPM-Based Framework for EOT Justification and Schedule Recovery2026-09-09T07:08:03+00:00Nizamuddin Fairus Zakaria[email protected]Risma Marleno[email protected]Laksono Djoko Nugroho[email protected]<p>Flooding is one of the most disruptive force majeure events in bridge construction, yet contractors frequently lack a structured framework to quantify its contractual and financial impacts. This paper presents a CPM-based framework — structured across Preventive, Responsive, and Recovery stages — to support Extension of Time (EOT) justification and schedule recovery in flood-affected bridge projects. A case study of the Kaliwekas-Bangeran 5 Bridge Replacement Project in Bojonegoro Regency (contract value: Rp 898,332,431; 90 calendar days) was used to validate the framework. Flood disruptions documented in field supervisor records and corroborated by BMKG rainfall data (peak: 56.4 mm/day, classified Heavy Rain) caused work stoppages on two activities: Structure Excavation (14 days) and Ferrocement (28 days). CPM re-analysis using ProjectLibre determined a 14-calendar-day project overrun, forming the legal basis for EOT entitlement under Articles 1244–1245 of the Indonesian Civil Code. Schedule recovery was achieved through incremental crashing of 12 critical activities using 3-hour overtime, yielding an optimal additional direct cost of Rp 30,130,315 — only 3.35% of total contract value. The framework was translated into a practical 21-step work guideline supported by a 12-document legal checklist, enabling contractors to substantiate EOT and acceleration cost claims with full technical and contractual accountability.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7090Operation Planning Analysis of Bus Rapid Transit on the Porong-Pasuruan Corridor Based on Travel Demand2026-09-09T07:21:01+00:00Dimas Wisnu Haryoko[email protected]Budi Witjaksana[email protected]Hanie Teki Tjendani[email protected]<p>Transportation is a strategic sector that plays a vital role in supporting economic growth. This study evaluates the demand for a BRT-based public transportation service along the Porong–Pasuruan corridor. Utilizing the Four-Step Model and a stated-preference approach, the study identifies potential passenger generation, calculates Vehicle Operating Costs (VOC), and evaluates investment feasibility using Net Present Value (NPV), Benefit-Cost Ratio (BCR), Internal Rate of Return (IRR), and Payback Period (PP) indicators. The results indicate that travelers’ willingness to shift modes reaches 59.8%, resulting in a potential BRT demand of 27,084 passengers per day. The proposed route connects Porong Terminal and Untung Suropati Terminal, with route lengths of 33.3 km for the Porong–Pasuruan direction and 33.5 km for the Pasuruan–Porong direction. The service is planned to use medium-sized buses with a capacity of 30 passengers and a service headway of 14.65 minutes. The financial feasibility analysis under the buy-the-service operational scheme yields a benefit-cost ratio value of 1.10, indicating that the financial benefits generated by the investment and operation of the BRT service exceed the costs incurred by the operator. Therefore, the project is considered financially feasible from the perspective of the service operator.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7091Water Balance Analysis for the Planning of Karangasem Small Reservoir in Mojokerto Regency2026-09-09T07:27:25+00:00Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]Revin Iqbal Ramadhan[email protected]<p>The Astacita Program initiated by President Prabowo's administration and the enactment of Presidential Regulation Number 2 of 2025 concerning the Acceleration of Development, Improvement, Rehabilitation, and Operation and Maintenance of Irrigation Networks to Support Food Self-Sufficiency have encouraged various efforts to strengthen national food security. One of the strategic efforts is ensuring the availability of irrigation water in both technical and non-technical irrigation areas. Government Regulation Number 30 of 2024 concerning Water Resources Management prioritizes the provision of water for public irrigation systems as the second priority after the fulfillment of basic daily water needs. The reservoir studied in this research is located in Karangasem Village, Bangsal District, Mojokerto Regency. The reservoir is an asset owned by the Karangasem Village Government and functions as a water storage facility planned to support both tourism activities and irrigation water supply. This study aims to analyze the water balance in the planning of the Karangasem Small Reservoir in Mojokerto Regency by comparing water availability discharge estimated using the F.J. Mock method with the irrigation water demand. The results of this study indicate that the optimization simulation of the Karangasem Small Reservoir, with a planned water surface area of 15.46 hectares, is capable of meeting the irrigation water demand under the cropping pattern of Rice I – Rice II – Secondary Crops (Palawija), starting from the first period of November. The implementation of this water management plan is expected to increase the cropping intensity to 300%.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7092Review of Cost and Time Performance on the Continuation Work of Al-Hasnie Road Improvement, Bantuas Village, Palaran District, Samarinda City2026-09-09T07:33:40+00:00Alviorika Dwiyana Ratu[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p>Road infrastructure plays a strategic role in supporting economic growth and community mobility. This study aims to analyze the cost and time performance of the Al-Hasnie Road Improvement Continuation Project located in Buntusu Village, Palaran District, Samarinda City using the Earned Value Management (EVM), Program Evaluation and Review Technique (PERT), and Estimate at Completion (EAC) approaches. The project contract value was Rp8,675,041,441 with an implementation duration of 100 calendar days. The research data were obtained from project implementation reports, including actual costs, work progress, and project schedules. The EVM analysis in the 9th week showed a Schedule Performance Index (SPI) value of 3.91 and a Cost Performance Index (CPI) value of 0.95. An SPI value greater than 1 indicates that the project was ahead of schedule, while a CPI value below 1 indicates that the actual costs were slightly higher than the planned costs. The Schedule Variance (SV) value of Rp34,000,000 indicates accelerated project progress, while the Cost Variance (CV) value of Rp92.4 billion shows a deviation from the planned budget. The PERT analysis indicated a 100% probability of project completion before 100 days, with an estimated completion time of 73 days. The EAC calculation estimated the total final project cost at Rp8,765,041,441. Overall, the project demonstrated good time performance due to accelerated work progress; however, stricter cost control is required to prevent budget overruns. This study shows that the combination of EVM, PERT, and EAC methods is effective for evaluating and predicting construction project performance quantitatively.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7093Analysis of Factors Causing Delays in the Sidorejo Road Handling Project, Lempake Village, North Samarinda District, Samarinda City2026-09-09T07:38:17+00:00Andri Purwoko[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p>The Sidorejo Road Handling Project in Lempake Village, North Samarinda District, Samarinda City is a road infrastructure project that experienced several delays during its execution. These delays were influenced by material, project management, equipment, labor, and environmental factors. This study aims to identify the dominant factors causing delays and to analyze the impact of material distribution delays on project cost and time. A quantitative approach was applied using Relative Importance Index (RII) analysis, Critical Path Method (CPM), S-Curve analysis, and material delay simulation. Data were collected through field observations, interviews, and project documentation. Results showed that material factors were the dominant cause of delays with a weight of 35%, followed by project management (25%), equipment (18%), labor (15%), and environmental factors (7%). Delays in material distribution caused a 10-day project delay and increased project costs by IDR 277,500,000 (3.44% of the planned budget). Simulation results further confirmed that greater material distribution delays lead to proportionally larger increases in project time and cost. These findings underscore the critical importance of effective material control systems and coordinated scheduling in road construction project management.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7094Risk Management Analysis on Performance Improvement in the Road Upgrading Project of the Long Tesak–Long Poq Village Main Road, Muara Ancalong District, East Kutai Regency2026-09-09T07:44:09+00:00Asrullah Asrullah[email protected]Risma Marleno[email protected]Esti Wulandari[email protected]<p>Road infrastructure development plays an important role in improving regional connectivity and supporting economic growth; however, its implementation often faces risks affecting project time, cost, and quality. This study aimed to identify dominant risks, analyze risk levels using the AS/NZS 4360 risk matrix, evaluate the influence of risks on project performance, and formulate mitigation strategies for the Long Tesak–Long Poq Road Improvement Project, Kutai Timur Regency. This study employed a descriptive quantitative approach using a survey method involving 30 respondents. Data were collected through questionnaires, interviews, and project documents, then analyzed using the ISO 31000 framework, AS/NZS 4360 risk matrix, and Pearson Product Moment correlation. The results showed that the dominant risks originated from time and environmental factors. The highest risk was weather disruption (R13 = 17.22), followed by material delay, work delay, schedule deviation, and high rainfall, each with a risk value of 16.40 (categorized as Extreme). Risk distribution indicated that 68% of risks were classified as High and 32% as Extreme. Correlation analysis revealed that time risk was the most dominant factor affecting project performance with r = 0.82, followed by environmental risk (r = 0.74) and cost risk (r = 0.68). Mitigation strategies based on the reduce approach, supported by engineering and administrative controls, were proven effective in reducing risk levels by an average of approximately 33%. Weather risk decreased from 17.22 to 11.20 (34.96%), while material delay risk decreased from 16.40 to 10.80 (34.15%). All risks previously categorized as Extreme were reduced to the High category. The study concludes that systematic risk management improves project performance by controlling time and environmental risks, resulting in better project outcomes in terms of schedule, cost, and quality.</p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7095Value Engineering Analysis on the Continuation Construction Work of the East Kutai District Police Headquarters (Mako Polres Kutai Timur)2026-09-09T07:47:41+00:00Murjito Murjito[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p><em>Value Engineering (VE) analysis was applied to the continuation project of the East Kutai District Police Headquarters (Mako Polres Kutai Timur) construction to optimize construction costs without reducing the building’s function and quality. Through Pareto analysis, the Traffic Police Headquarters Building (Mako Satlantas) and Supporting Facilities were identified as the dominant cost components, amounting to IDR 20,446,535,470.42 or 56.52% of the total project cost before tax. Based on the criteria of high cost, large work volume, and cost-saving potential, the conventional red brick wall system (baseline A0) was selected for evaluation against three alternative wall materials, namely AAC lightweight brick (A1), lightweight precast panel (A2), and high-quality pressed concrete block (A3). The results of the multi-criteria evaluation indicated that AAC lightweight brick (A1) was the most optimal alternative. The implementation of AAC lightweight brick generated direct cost savings of IDR 131,977,910.16 or 8.20% of the initial wall system cost and contributed 0.33% savings to the total project value. In addition, the use of AAC lightweight brick reduced the building dead load by 335.09 tons (63.89%) and accelerated wall construction duration from 91 days to 52 days, resulting in a schedule compression of 42.86%. The study concludes that the Value Engineering method is effective in improving project cost efficiency and value without reducing the building’s function and quality.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7100Analysis of the Potential of Raw Water Sources on Maratua Island, Berau Regency, Indonesia–Philippines Border Area2026-09-10T04:22:31+00:00Rahmat Sujatmiko[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p><em>Clean water is a fundamental necessity for human life and regional development. Maratua Island, as one of Indonesia’s outermost small islands located near the Indonesia–Philippines border, faces significant challenges in securing raw water sources due to its karst geological conditions, lack of surface water, and high risk of seawater intrusion. These conditions are further worsened by increasing water demand driven by population growth and the development of the tourism sector. This study aims to analyze the potential of raw water resources and evaluate the feasibility of constructing the Maratua Raw Water Reservoir as a sustainable solution for clean water supply. The research method applies a feasibility study approach covering technical, economic, and financial aspects. The analysis is conducted using investment indicators such as Net Present Value (NPV), Internal Rate of Return (IRR), Benefit Cost Ratio (BCR), and Payback Period (PP). In addition, a sensitivity analysis is performed to assess the project’s resilience to changes in investment costs and benefits. The results show that the total investment cost for the reservoir construction is IDR 48,000,000,000, with annual operation and maintenance costs of IDR 4,451,000,000. The feasibility analysis indicates an NPV of IDR 14,393,863,242, an IRR of 14.09%, a BCR of 1.15, and a Payback Period of 5.56 years. These results demonstrate that the project is feasible and capable of providing economic benefits while supporting sustainable clean water supply for the Maratua Island community. The sensitivity analysis also shows that the project remains feasible even when investment costs and benefits fluctuate by up to 15%.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7101Risk Analysis of the Construction Project for the Community Hall (BPU) Building in Jembayan Tengah Village, Kutai Kartanegara Regency, East Kalimantan2026-09-10T04:26:56+00:00Suriansyah Suriansyah[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p><em>The construction of the Community Hall (Balai Pertemuan Umum/BPU) Building in Jembayan Tengah Village faces various risks that may affect project performance in terms of time, cost, quality, and occupational health and safety (OHS). This study aims to identify the level of risks, determine dominant risks, and evaluate the effectiveness of mitigation strategies in improving project performance. The research employs a descriptive quantitative approach using a survey method through Likert-scale questionnaires, interviews, and project document analysis. The analysis is conducted using probability (P), impact (I), and risk level (R = P × I) assessment. The results show that there are 14 main risks, categorized into technical (35.71%), managerial (28.57%), labor-related (21.43%), and environmental (14.29%) risks. A total of 78.57% of the risks fall into the high and very high categories, with an average risk value of 13.26. The dominant risks are material delays (R = 17.22), schedule delays (R = 16.00), occupational accidents (R = 15.48), and poor concrete quality (R = 15.12). The main contributing factors are logistics and management issues, accounting for 57.14% of the causes. The implementation of mitigation strategies, including avoidance, reduction, transfer, and acceptance, successfully reduced the average risk level by 25.40%. Improvements were observed in project performance, with reductions in time (20.92%), cost (22.49%), quality (23.36%), and OHS risks (30.55%). This study demonstrates that systematic and structured risk management can improve construction project performance more effectively, efficiently, and safely.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7102Analysis of the Effectiveness of Landslide Mitigation Work on Al-Hasnie Road, Bantuas Urban Village, Palaran District, Samarinda City2026-09-10T04:30:46+00:00Taufik Qurohman[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p><em>Road landslides are one of the infrastructure problems frequently occurring in areas with steep topography and high rainfall, including Samarinda City. One of the affected locations is Al-Hasnie Road in Bantuas Urban Village, Palaran District, which caused road damage and traffic disruption. These conditions require effective mitigation through design evaluation to ensure safer and more efficient landslide handling structures. This study aims to analyze the effectiveness of landslide mitigation work through a review design approach on Al-Hasnie Road, Samarinda City. The research employed an evaluative method by analyzing both the existing design and an alternative design. The evaluation focused on retaining structures, drainage systems, construction methods, and project cost and time efficiency. The results showed that the existing design experienced overdesign conditions in the use of bored piles and structural concrete, resulting in cost and implementation inefficiencies. Through the review design process, reductions were made in bored pile length, concrete volume, and steel reinforcement without reducing structural function. The analysis showed that project costs decreased from IDR 2,189,675,607.51 to IDR 1,650,468,595.85, resulting in cost savings of 24.63%. In addition, project duration decreased from 75 days to 61 days, achieving a time efficiency of 18.67%. Therefore, the alternative design was considered more effective, efficient, and feasible for implementation in the landslide mitigation work on Al-Hasnie Road.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7103Risk Management Analysis on Project Performance Improvement of Road Infrastructure Development: Damanhuri Road Improvement Project, Sungai Pinang District, Samarinda City2026-09-10T04:35:01+00:00Winaldi Ratu[email protected]Laksono Djoko Nugroho[email protected]Ony Frengky Rumihin[email protected]<p><em>Road construction projects involve a high level of risk due to technical, managerial, operational, environmental factors, and uncertainties during project execution. This study aims to identify project risks, determine risk levels, analyze the relationship between risk and project performance, and develop risk management strategies for the Damanhuri Road Improvement Project. The study employed a quantitative descriptive approach based on ISO 31000:2018 risk management guidelines and risk assessment using the equation R = Likelihood (L) × Consequence (C). Data were collected through field observations, interviews, and questionnaires distributed to 36 respondents involved in the project. The results identified 20 major risks, which were classified into five categories: technical risks (25%), time-related risks (20%), cost risks (15%), managerial risks (20%), and environmental and occupational health and safety risks (20%). Technical risk was found to be the most dominant category. Based on the risk assessment results, four risks were classified as very high risk, namely material delay (R6) with a score of 19.8, poor coordination (R13) with 17.2, non-compliant materials (R2) with 16.8, and concrete quality issues (R5) with 16.4. These dominant risks had direct impacts on project performance, particularly on the time aspect through project delays, on cost through waste and rework, and on quality through reduced construction performance. The risk management strategies applied included avoid, reduce, transfer, and accept, with the reduce strategy becoming the dominant approach, accounting for approximately 70% of the implemented mitigation measures. These actions included strengthening material control, improving stakeholder coordination, enhancing quality supervision, and implementing occupational health and safety management systems. The findings indicate that project success is strongly influenced by effective, structured, and sustainable risk management practices to ensure the achievement of project objectives in terms of time, cost, and quality.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7104The Influence of Technology Utilization and E-Procurement Implementation on Procurement Performance in Direct Procurement at the Public Works and Spatial Planning Office of West Kutai Regency2026-09-10T04:43:36+00:00Domy Stephens[email protected]Risma Marleno[email protected]Retno Hastijanti[email protected]<p><em>The development of information technology has encouraged governments to improve the effectiveness, efficiency, transparency, and accountability of goods and services procurement through the implementation of E-Procurement. However, direct procurement at the Public Works and Spatial Planning Office (Dinas PUPR) of West Kutai Regency still faces obstacles such as procurement delays, high administrative costs, limited technological infrastructure, and low human resource readiness. This study aims to analyze the influence of technology utilization and E-Procurement implementation on direct procurement performance at the said office. A mixed methods approach was employed, combining quantitative and qualitative methods. Quantitative analysis was conducted using descriptive statistics, classical assumption tests, and the Partial Least Square-Structural Equation Modeling (PLS-SEM) method using SmartPLS 3.2.8. Data were collected from 38 respondents, six key informants, and one Focus Group Discussion (FGD) session. Results showed that E-Procurement implementation had the most dominant influence on procurement performance with a path coefficient of 0.52 and T-statistic of 4.10, while technology utilization had a significant influence with a coefficient of 0.38 and T-statistic of 2.75. The R-Square value of 0.74 indicates that 74% of the variation in procurement performance can be explained by both variables. The study concludes that the integration of technology and E-Procurement significantly improves the efficiency, transparency, accountability, and quality of direct procurement performance.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7105Feasibility Study of Ded Work for Spam Punan Malinau, Berau Regency2026-09-10T05:07:14+00:00Khoiri Mahmud[email protected]Risma Marleno[email protected]Retno Hastijanti[email protected]<p><em>The availability of clean water is one of the most essential basic needs of the community in supporting public health, quality of life, and regional development. Limited access to clean water remains a problem in several remote areas of Berau Regency, one of which is Punan Malinau Village, Segah District. The community still depends on surface water sources and rainwater, whose quality and quantity are not yet adequate. Therefore, it is necessary to plan the development of a Drinking Water Supply System (SPAM) through the preparation of a Feasibility Study and Detailed Engineering Design (DED) to determine the investment requirements and the economic feasibility level of the project. This study aims to determine the amount of investment cost and operational cost of the Punan Malinau SPAM development project and to analyze the project’s economic feasibility using the Net Present Value (NPV), Internal Rate of Return (IRR), Benefit Cost Ratio (BCR), and Payback Period (PP) methods. The research method was carried out through the collection of technical and financial data, calculation of investment costs, operation and maintenance costs, water tariff revenues, and investment feasibility analysis based on the project life cycle. Based on the analysis results, the total investment cost for SPAM development was Rp 15,490,800,000 with operation and maintenance costs amounting to Rp 142,437,924 per year or Rp 11,869,827 per month. Revenue from water tariffs amounted to Rp 151,200,000 per year, resulting in a net cash flow of Rp 8,762,076 per year. The economic feasibility analysis showed a Net Present Value (NPV) of +Rp 893,361,256, an Internal Rate of Return (IRR) of 10.85%, a Benefit Cost Ratio (BCR) of 1.05, and a Payback Period (PP) of 8.05 years. Based on these results, the SPAM development project in Punan Malinau, Berau Regency, is considered economically feasible to be implemented because all investment indicators meet the feasibility criteria. In addition, this project is also expected to improve community access to clean water, enhance environmental health quality, and support sustainable regional development.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7106Feasibility Analysis of the Archive Depot Building, Kutai Kartanegara Regency2026-09-10T05:14:06+00:00Andi Arrafi'u Saputra[email protected]Risma Marleno[email protected]Esti Wulandari[email protected]<p><em>The Archive Depot Building of Kutai Kartanegara Regency is planned as an archive storage facility to support safer, more organized, and efficient management of regional government archives. Existing conditions indicate that most archives are still stored in rooms that do not meet archival standards, thereby increasing the risk of document damage and loss. Therefore, a feasibility analysis is required to assess whether the construction of the archive depot building is feasible in terms of technical, economic, and social aspects. This study aims to analyze the feasibility of constructing the Archive Depot Building of Kutai Kartanegara Regency using qualitative and quantitative approaches through technical aspect analysis, Cost-Benefit Analysis (CBA), and Social Impact Assessment (SIA). The economic analysis uses the indicators of Economic Net Present Value (ENPV) and Economic Benefit-Cost Ratio (EBCR) with a project life of 50 years and a discount rate of 10%. The results show that the project is technically feasible because the location, building design, construction methods, and availability of resources meet the required standards. The total project investment cost is Rp5,767,502,000 with an ENPV value of Rp597,498,000 and an EBCR value of 1.07. From the social aspect, the construction of the building provides positive impacts in the form of local employment opportunities, increased community economic activities, and improved quality of public services. The emerging social risks are relatively low and still manageable. Based on the analysis of technical, economic, and social aspects, the construction of the Archive Depot Building of Kutai Kartanegara Regency is considered feasible to support more effective, transparent, and accountable governance.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7107Investment Feasibility Analysis of the Construction of Kapten Soedjono–Tanah Merah Road, Samarinda City2026-09-10T05:41:50+00:00Agung Harinugraha[email protected]Risma Marleno[email protected]Erni Puspanantasari Putri[email protected]<p><em>Kapten Soedjono–Tanah Merah Road in Samarinda City is a strategic road segment that supports community mobility and logistics distribution. However, the current road condition still faces several issues such as flooding, heavy vehicle congestion, road damage, and high vehicle operating costs. Therefore, a technical and investment feasibility analysis is required to determine the feasibility level of the road development project. This study aims to determine the amount of investment costs and vehicle operating costs, as well as to analyze the investment feasibility of the Kapten Soedjono–Tanah Merah Road development using the Net Present Value (NPV), Internal Rate of Return (IRR), Benefit Cost Ratio (BCR), and Payback Period (PP) methods. The research method involves collecting technical and financial data, analyzing investment costs, analyzing Vehicle Operating Costs (VOC), and conducting economic feasibility analysis over a 20-year project life span with a 10% discount rate. The results show that the total investment cost for the road construction is Rp851,347,338,153, with total Vehicle Operating Costs of Rp10,233.31/vehicle-km. The feasibility analysis results indicate a Net Present Value (NPV) of Rp3,851,132,008,207, an Internal Rate of Return (IRR) of 62%, a Benefit Cost Ratio (BCR) of 5.52, and a Payback Period (PP) of 1.54 years. Based on these results, the development of the Kapten Soedjono–Tanah Merah Road in Samarinda City is considered feasible to implement, as all investment indicators meet the feasibility criteria. This project is expected to improve road service quality, facilitate community mobility, reduce transportation costs, and support economic growth in Samarinda City.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7108Application of Value Engineering in Cost Optimization and Function of Rehabilitation Work on Irrigation Network D.I. Pesap, East Kutai Regency2026-09-10T05:45:42+00:00Gandung Dwi Kuncoro[email protected]Risma Marleno[email protected]Retno Hastijanti[email protected]<p><em>Irrigation infrastructure is fundamental to agricultural productivity and national food security. The D.I. Pesap irrigation network in East Kutai Regency, East Kalimantan, required rehabilitation due to physical deterioration of canals, inspection roads, and hydraulic structures. The rehabilitation project, however, encountered challenges related to high construction costs that were not fully proportional to the functional improvements achieved. Two work items—the inspection road and the secondary canal—dominated the budget, collectively accounting for 84.16% of total analyzed project costs. This study applied the Value Engineering (VE) methodology to systematically optimize costs and functions without reducing quality or performance. Using a quantitative descriptive approach, the analysis followed five VE phases: Information Phase, Function Analysis Phase, Creative Phase, Evaluation Phase, and Recommendation Phase. Data were collected from the Bill of Quantities (BOQ), working drawings, technical specifications, and field observations from the 2025 Fiscal Year project of the Kalimantan IV River Basin Hall. Pareto analysis was used to identify dominant cost items. Function analysis revealed cost-worth imbalances in both work items. Creative alternatives were developed through material substitution and design optimization. Results demonstrate that VE produced a 26.12% cost saving for inspection road works through substitution of local soil combined with sirtu material and mechanical vibratory roller compaction, and an 11.75% saving for secondary canal works through concrete grade optimization (fc'15 MPa to fc'12.5 MPa) with reduced reinforcement and selective waterstop placement. Total cost savings reached IDR 1,271,645,498, equivalent to 19.72% of the initial analyzed project cost. Functional evaluation confirmed that the inspection road's operational access function and the secondary canal's hydraulic conveyance function were fully maintained. These findings demonstrate that Value Engineering effectively enhances project value by eliminating unnecessary costs while preserving infrastructure function and quality.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7109Risk Control Analysis on Improving Construction Work Performance in the Development of a B3 (Hazardous and Toxic Waste) Storage Warehouse at Mankujaya Linggang Hospital2026-09-10T05:50:14+00:00Aleksandeer Meiruddi Indrilackson[email protected]Risma Marleno[email protected]Erni Puspanantasari Putri[email protected]<p><em>Construction projects, particularly healthcare support facilities, face high levels of uncertainty and risk that may affect project performance in terms of time, cost, quality, and safety. This study aimed to analyze and control risks in the construction of the Temporary Storage Warehouse for Hazardous and Toxic Waste (B3) at RSUD Mangkujaya Linggang, West Kutai Regency, using the Hazard Identification, Risk Assessment and Risk Control (HIRARC) and House of Risk (HOR) methods. This research applied a mixed-method approach through observations, interviews, questionnaires to 15 respondents, FGD, and project document analysis. Risk levels were assessed using Likelihood (L) and Severity (S), while mitigation priorities were determined using HOR analysis. The results identified 12 major risks, with dominant risks consisting of material delay (R = 16.79), work accidents (R = 16.62), and structural work delay (R = 15.99). A total of 75% of risks were classified as high risk and 25% as medium risk. The main risk causes were material distribution delays, low K3 compliance, and limited workforce competency. Priority mitigation strategies included K3 training and mandatory PPE use, technical supervision, and logistics planning with material buffer stock. Risk control implementation reduced project risks by approximately 26–35%, improved cost efficiency by 10–15%, and increased the Project Performance Index (PI) from 92% to 105%. The study concludes that integrating HIRARC and HOR is effective in reducing project risks and improving overall construction project performance.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7110Financial Feasibility and Resilience of Water Pump House Automation Investment: An NPV, IRR, ROI, and BCR Approach with Macroeconomic Sensitivity Scenarios2026-09-17T06:42:38+00:00Trisna Hadi Sanjaya[email protected]Esti Wulandari[email protected]Andi Patriadi[email protected]<p><em>Modernizing water utilities under Industry 4.0 requires capital investment in automation, yet such investments must be justified by rigorous financial appraisal and tested for robustness against economic uncertainty. This study evaluates the financial feasibility and resilience of a SCADA-PLC-VSD smart pumping system installed at the Kandangan Pump House of Perumda Air Minum Surya Sembada, Surabaya, Indonesia. Using a cost–benefit framework applied to secondary data over a four-year economic life at a 6% discount rate, the staged investment of Rp 600,042,690 was appraised against combined annual savings of Rp 729,387,560 through four indicators—Net Present Value (NPV), Internal Rate of Return (IRR), Return on Investment (ROI), and Benefit–Cost Ratio (BCR)—and stress-tested under five macroeconomic sensitivity scenarios. The investment proved highly feasible (NPV Rp 1,705,107,332.45; IRR 105.43%; ROI 345.71%; BCR 4.46) and remained feasible under every scenario. A 15% reduction in benefits was the most influential parameter, whereas higher electricity tariffs and minimum wages improved feasibility, since the project's benefits are avoided costs. The study offers water utilities a replicable techno-economic framework for justifying and de-risking infrastructure automation.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7111Bts. Kab. Sidoarjo-Mojokerto Regency Using Bina Marga Guidelines2026-09-17T06:46:15+00:00Andy Martono[email protected]Budi Witjaksana[email protected]Andi Patriadi[email protected]<p><em>Public participation in reporting road conditions is increasing through digital-based complaint services. However, the handling of these complaints remains hampered by data inaccuracies and the absence of a digital system to oversee repair operations. This situation highlights the need for a system that documents damage history and repair methods, alongside WebGIS-based spatial mapping of repair activities; such a system would enable data to be documented, tracked, and analyzed more systematically, thereby facilitating the monitoring and evaluation of road maintenance within a unified framework. The research object is the Bts. Kab. Sidoarjo - Mojokerto Regency section. Road damage complaints received in the system are then identified through surveys and measurements of the damage conditions recorded according to Bina Marga guidelines. Reports and condition assessments are used to determine standard repair methods. The results show that road pavement damage consists of potholes with a depth of >50 mm, potholes with a depth of <50 mm, and bumps with a depth of >50 mm. The standard repair method for potholes and bumps with a depth of >50 mm is P5: Patching. For potholes with a depth of <50 mm, the repair method is P6: Leveling. Road damage repairs are digitized directly using webGIS through damage distribution maps.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7112Productivity Analysis of Amphibious Heavy Equipment Hitachi MA200G Excavator in the Masangan River Normalization Works, Pasuruan Regency2026-09-17T06:53:13+00:00M Tafsir[email protected]Esti Wulandari[email protected]Andi Patriadi[email protected]<p><em>The normalization of the Masangan River in Pasuruan Regency is carried out to address sedimentation that reduces the river's capacity and increases the risk of flooding. Normalization work requires heavy equipment capable of operating on muddy and watery terrain, one of which is the Hitachi MA200G Amphibious Excavator. This study aims to analyze the productivity of the Hitachi MA200G Amphibious Excavator in the normalization work of the 6.53 km-long Masangan River using the 2026 Unit Price Analysis (AHSP) method. The analysis is based on data on work volume, cycle time, equipment capacity, work efficiency, and field conditions. The research results are expected to indicate the level of equipment productivity and serve as a reference for the selection and management of effective and efficient heavy equipment in river normalization work.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7113Analysis of the Impact of Increased Storage Capacity on Nipah Reservoir Operating Policy in Madura, Indonesia2026-09-17T06:56:50+00:00Bakti Yudi Firmanto[email protected]Andi Patriadi[email protected]Esti Wulandari[email protected]<p><em>Nipah Reservoir serves irrigation, raw water supply, and flood control functions in Sampang Regency, East Java, Indonesia. Modifications to the reservoir design due to unresolved land acquisition issues led to a reduction in effective storage capacity through lowering the spillway crest elevation. This condition affected reservoir operation and reduced its ability to meet water demands, particularly for irrigation. This study evaluates the operational performance of Nipah Reservoir under a proposed increase in storage capacity by raising the spillway crest elevation to +44.50 m. Reservoir operation simulations were conducted using hydrological data, storage characteristics, water demand, and operating rules. The analysis focuses on changes in storage capacity, water supply reliability, and reservoir release patterns. The results are expected to show that increasing the effective storage capacity improves irrigation water supply reliability and enhances reservoir operational efficiency. The findings provide a basis for developing a more optimal and sustainable reservoir operation policy to support future water resource management.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7114Analysis of Dominant Factors Affecting Detail Engineering Design (DED) Development Performance in the Design and Build Project of Muna Barat Regional General Hospital Using a PLS-SEM Approach2026-09-17T07:01:20+00:00Abdul Khohar[email protected]Budi Wulandari[email protected]Andi Patriadi[email protected]<p><em>This study analyzes the influence of Basic Design quality, the level of compliance with the Commitment-Making Officer Requirement Document (DKPPK), and conformity with site conditions on the performance of Detail Engineering Design (DED) development in the Muna Barat Regional General Hospital construction project under the Design and Build scheme. The research employed a quantitative explanatory approach based on Partial Least Squares Structural Equation Modeling (PLS-SEM) using SmartPLS 4 software version 4.1.1.8. Data were obtained from 31 project stakeholder respondents with a 100% response rate. The outer model evaluation results indicate that all constructs satisfy convergent validity and reliability requirements. The composite reliability values for each construct are as follows: Basic Design 0.941; DKPPK 0.900; Site Conditions 0.897; and DED Development Performance 0.897, with all construct AVE values > 0.50. The R-square value of 0.871 indicates that 87.1% of the variation in DED development performance is explained by the three exogenous variables. The hypothesis testing results indicate that only the site conditions variable has a significant effect on DED development performance, with a path coefficient of β = 0.763; t-statistic = 3.681; p-value = 0.000; and effect size of 1.212. Meanwhile, Basic Design (β = 0.249; p = 0.287) and DKPPK (β = -0.022; p = 0.926) are not significant. These findings confirm that actual site conditions constitute a critical factor in the success of DED development in Design and Build hospital projects located in archipelagic regions.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7115Analysis of Cost and Time Performance in the Construction of the Central Kalimantan People's School Project2026-09-17T07:08:42+00:00Vendy Eka Saputra[email protected]Budi Witjaksana[email protected]Andi Patriadi[email protected]<p><em>The Central Kalimantan People's School Development Project is a construction project implemented at several locations with varying site conditions, including peat soil, limited accessibility for mobilization, extreme weather conditions, and material availability constraints. These conditions have the potential to affect project cost and completion time, making it necessary to analyze their impact on project performance. This study aims to analyze the cost and time performance of the Central Kalimantan People's School Development Project and to evaluate schedule control using the Critical Path Method (CPM). The research employs a case study approach with descriptive and evaluative analysis methods. The data used in this study include the initial contract, contract addendum, project schedule (time schedule), and project progress reports. Cost analysis was conducted by comparing the initial contract value with the amended contract value, while time analysis was carried out using CPM to identify the critical path and activities affecting the project completion duration. The results indicate that site conditions significantly influence both project cost and execution time. The contract value increased from IDR 985,900,000,000 to IDR 1,035,519,567,108, representing an increase of 5.03%. Furthermore, CPM analysis identified critical activities that require close monitoring to maintain the project completion target. The application of CPM proved useful in supporting schedule control and decision-making during project execution.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7116Determination of Road Maintenance Priority Sequence with Analytic Hierarchy Process (AHP) and SWOT Approach2026-09-18T04:07:31+00:00I Ketut Nagageni Halilintar Mahadewa[email protected]Ony Frengky Rumihin[email protected]Iswandaru Widyatmoko[email protected]<p><em>The limited road maintenance budget requires the government to determine handling priorities objectively and strategically. This study aims to produce recommendations for road infrastructure maintenance priorities as a basis for decision-making on the Wlingi–Kepanjen–Turen road segment. The method used is an integration of the Analytical Hierarchy Process (AHP) and Strengths, Weaknesses, Opportunities, Threats (SWOT). AHP is used to determine the importance level of each road maintenance criterion based on expert assessments, while SWOT is used to identify internal and external factors affecting road maintenance policies. The results Based on the integrated AHP–SWOT approach, the priority ranking for road maintenance is as follows: the Kepanjen–Gondanglegi Road as the highest priority, followed by the Blitar Regency Boundary–Kepanjen Road, the Wlingi City Boundary–Malang Regency Boundary Road, and the Gondanglegi–Turen Road as the lowest priority. This approach provides a more comprehensive basis in the preparation of road maintenance programs so that budget allocation can be carried out effectively, transparently, and accountably. This research is expected to serve as a reference for road management agencies in determining targeted maintenance priorities.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7117Ranking the Indicators of Low-Carbon Construction Transition Readiness in Bali’s Tourism Buildings Using the Relative Importance Index2026-09-18T04:12:55+00:00I Wayan Wiraga[email protected]Wayan Sri Kristinayanti[email protected]I Gusti Agung Arie Krismayanti[email protected]<p><em>The building and construction sector accounts for roughly one third of global carbon emissions, and the rapid, largely unregulated expansion of hotels, resorts, and villas across Bali is intensifying the embodied and operational carbon footprint of one of Indonesia’s most important tourism destinations. However, Indonesia has committed to the Paris Agreement and a 2060 net-zero target; no empirically grounded instrument yet measures how prepared the local construction industry is to transition toward low-carbon practice in the tourism-building segment. This study addresses that gap by identifying and ranking the indicators that shape low-carbon construction transition readiness in Bali’s tourism buildings. A cross-sectional survey was administered to 50 organizations spanning contractors, design and supervision consultants, project owners and developers, local government technical officials and material suppliers, selected through purposive sampling. Twenty-five indicators grouped into six constructs, organizational readiness, low-carbon technology readiness, low-carbon material readiness, regulatory support and incentives, human-resource capacity, and overall transition readiness, were measured on a five-point Likert scale. The Relative Importance Index (RII) was computed for each indicator and aggregated at the construct level to establish a dominance ranking. Results show that organizational readiness recorded the highest aggregate importance (RII = 0.834), driven by dedicated budget allocation for low-carbon innovation and materials (RII = 0.852) and the availability of internal policies and standard operating procedures (RII = 0.844). Regulatory support and incentives ranked lowest across all constructs (RII = 0.699), with clarity of green-building regulation obtaining the single lowest score (RII = 0.680). A consistent pattern emerged in which cognitive and organizational preparedness outpaces the enabling ecosystem of finance, certification data, and regulation. The findings indicate that practitioners in Bali are internally and technically ready to transition but are constrained by weak regulatory signals and the reluctance to absorb early capital expenditure. The ranked indicators provide an evidence base for prioritizing policy interventions and a foundation for subsequent structural modeling of transition readiness.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7118Prioritizing Green Construction Practices in the Balinese Construction Industry: A Relative Importance Index Analysis2026-09-18T04:16:46+00:00Wayan Sri Kristinayanti[email protected]I Gusti Agung Istri Mas Pertiwi[email protected]I Gusti Agung Arie Krismayanti[email protected]<p><em>The construction sector drives economic growth, yet remains a major consumer of energy and raw materials, and a significant source of carbon emissions and solid waste. Green construction practices offer a strategic response, but their adoption in Bali is shaped by a distinctive intersection of tourism-driven development pressure and deeply rooted local cultural values. This study identifies and prioritizes the green construction practices that construction practitioners in Bali consider most important. Using an exploratory sequential mixed-methods design, indicators were first established through literature synthesis and semi-structured interviews, then evaluated quantitatively. A questionnaire employing a five-point Likert scale was distributed to 50 green construction practitioners, project managers, site managers, field supervisors, and green construction professionals in Denpasar and Badung through stratified random sampling. The data were analyzed using the Relative Importance Index (RII) to rank 16 indicators across four dimensions: passive design and cultural adaptation; energy efficiency and water conservation; local and environmentally friendly material procurement; and project environmental management. The results show that health and comfort of the work environment (RII = 0.832), local bio-based materials (0.824), and rooftop photovoltaics (0.820) ranked highest, whereas rainwater harvesting (0.772) and low embodied carbon (0.780) ranked lowest. The priorities reveal that practitioners integrate conventional green metrics with Balinese local wisdom, notably the natah concept and Asta Kosala Kosali principles, while water conservation and carbon accounting lag behind. These findings provide an evidence base for green procurement standards, capacity-building, and policies to accelerate sustainable construction in Bali.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7119Analysis of Factors Contributing the Acceleration of Stone Masonry Construction Activities Using the Fast-Track Method in the Kedunglarangan River, Pasuruan Regency2026-09-18T04:20:43+00:00Muhammad Inan Kautsar[email protected]Andi Patriadi[email protected]Esti Wulandari[email protected]<p><em>The stone masonry work for riverbank reinforcement along the Kedunglarangan River in Pasuruan Regency is a crucial mitigation effort aimed at controlling erosion, preventing riverbank failures, and protecting nearby residential areas and public infrastructure. The increasing risk of damage caused by river scouring and landslides, which may disrupt major transportation routes and community activities, necessitates the timely completion of construction works without compromising quality standards. Therefore, an effective project acceleration strategy is required through the implementation of the Fast-Track method. This study aims to analyze the factors that contribute to accelerating stone masonry construction activities in the Kedunglarangan Riverbank Reinforcement Project using the Fast-Track approach. A quantitative descriptive method was employed by identifying construction activities that could be executed concurrently while maintaining the logical dependencies among tasks. Research data were collected from project schedules, technical documents, field observations, and interviews with project stakeholders. The results indicate that project duration can be significantly reduced through the optimization of material availability, effective workforce allocation, adequate equipment readiness, improved coordination among construction activities, and the implementation of overlapping work sequences. The most influential factors in the successful application of the Fast-Track method are the continuity of material supply and the synchronization of field operations. The application of the Fast-Track method has proven effective in shortening the project duration, enabling faster completion of riverbank reinforcement works and reducing the potential risks of environmental damage and disruptions to community activities.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabayahttps://conference.untag-sby.ac.id/index.php/icef-tags/article/view/7120Time Management Analysis of Project Delays Using the Earned Value Method: A Case Study of the Mbambang River Gabion Construction Project, Malang Regency2026-09-18T04:25:36+00:00Surya Adi Rinekso[email protected]Esti Wulandari[email protected]Andi Patriadi[email protected]<p><em>Construction project delays are among the most common challenges affecting project performance, particularly in terms of schedule achievement, resource utilization, and overall project efficiency. The gabion retaining structure construction project at the Mbambang River, Malang Regency, experienced schedule deviations that potentially impacted the timely completion of the project. Effective time management is therefore essential to evaluate project performance and identify corrective actions required to mitigate delays. This study aims to analyze project time management associated with construction delays in the Mbambang River gabion works using the Earned Value Method (EVM). The Earned Value Method was employed as an integrated project control technique that combines schedule performance, cost performance, and physical work progress into a single analytical framework. The analysis was conducted using key EVM indicators, including Planned Value (PV), Earned Value (EV), Actual Cost (AC), Schedule Variance (SV), and Schedule Performance Index (SPI). Project data were obtained from the baseline schedule, progress reports, and actual project implementation records throughout the construction period. These indicators were subsequently used to assess schedule performance, determine the extent of project delays, and estimate the projected completion time based on actual project progress. The results indicate that the project experienced schedule delays, as reflected by negative Schedule Variance (SV) values and a Schedule Performance Index (SPI) of less than one during several reporting periods. These findings demonstrate that the actual work progress achieved was lower than the planned progress, resulting in delays in project execution. The application of EVM proved effective in providing a comprehensive assessment of project performance, enabling early detection of schedule deviations and supporting decision-making processes for implementing acceleration strategies. Therefore, the Earned Value Method can serve as a reliable project control tool for improving time management performance in river protection projects, particularly those involving gabion construction works.</em></p>2026-09-23T00:00:00+00:00Copyright (c) 2026 Proceeding International Civil Engineering Forum Untag Surabaya