The Hidden Cost of Quality Failure in Road Construction: Evidence from a Strategic Infrastructure Project in Batam, Indonesia

Authors

  • Martina Magdalena Tuulima Universitas 17 Agustus 1945 Surabaya
  • Hanie Teki Tjendani Universitas 17 Agustus 1945 Surabaya
  • Bambang Trigunarsyah RMIT University, Melbourne

Keywords:

contextual RBQM model, quality governance, quality-severity FMEA, risk-based quality management, road infrastructure construction

Abstract

Quality control in Indonesian road construction remains structurally reactive: risk management and quality assurance operate as independent functions without a shared analytical framework, leaving oversight resources uniformly distributed regardless of actual risk exposure. This study examines how Risk-Based Quality Management (RBQM) was applied throughout the Hang Tuah Road Widening Project in Batam City, Indonesia (a high-complexity arterial intervention with a final contract value of IDR 68.28 billion under continuous traffic conditions), and identifies the structural factors constraining or supporting its effectiveness. A retrospective single-case study design is employed, drawing on 34 primary project documents and semi-structured interviews with nine key informants, supplemented by Failure Mode and Effects Analysis (FMEA) incorporating a Quality-Severity modification that isolates specification non-conformance magnitude as the primary risk scoring dimension. Findings establish that none of the five core RBQM elements was formally operationalized at any project stage, despite concurrent availability of four structural enabling conditions that remained collectively underutilized. Three dominant quality risk events were identified, all classified as High priority with RPN-Quality values ranging from 336 to 432; Detection scores of 8 on two events confirm the monitoring architecture was structurally incapable of intercepting deviations before they became irremediable. Two governance deficiencies emerged as primary determinants: the absence of a formal risk register as the calibrating instrument for proportionate oversight allocation, and exclusive reliance on binary pass/fail evaluation incapable of detecting adverse parameter trends prior to specification breach. These findings yield two practitioner-oriented outputs: a Contextual RBQM Model structuring five sequentially interdependent governance elements, and an RBQM Implementation Guideline translating the model into operational steps for comparable road infrastructure projects.

Downloads

Published

2026-09-23

Issue

Section

Articles